description: "FMEA Analysis has an auto-function to help the users quickly complete the risk evaluation through the **Risk Evaluation pane**. To access the **Risk Evaluation pane** from Excel's ribbon, select **Risk Evaluation** from the Task Pane group. ![](https://www.iqasystem.com/wp-content/uploads/Turn-on-Risk-Evaluatio-pane.png) This is how…"
url: "https://www.iqasystem.com/support/fmea-analysis/risk-evaluation-for-fmea/"
updated: "2022-03-28"
category: How To
---

# Risk Evaluation for FMEA

FMEA Analysis has an auto-function to help the users quickly complete the risk evaluation through the **Risk Evaluation pane**. To access the **Risk Evaluation pane** from Excel's ribbon, select **Risk Evaluation** from the Task Pane group.

![](https://www.iqasystem.com/wp-content/uploads/Turn-on-Risk-Evaluatio-pane.png)

This is how it looks

![](https://www.iqasystem.com/wp-content/uploads/Risk-Evaluation-task-pane.png)

## 1. Specify the risk index column

The section **Index Columns** of the task pane allow the users to set up the index columns in the worksheet. You can specify the risk index columns before the recommended actions (first rating) and/or after the recommended actions are taken (re-rating).

![](https://www.iqasystem.com/wp-content/uploads/Index-Columns.png)

1. Severity: Specify the column used for severity ranking.
2. Occurrence: Specify the column used for occurrence ranking.
3. Detection: Specify the column used for detection ranking.
4. Risk Indicator: Specify the column used as the risk indicator column. Risk indicator can be Risk Priority Number, Critical Number, SOD,...
5. Re-Severity: Specify the column used for severity ranking after the recommended actions are taken.
6. Re-Occurrence: Specify the column used for occurrence ranking after the recommended actions are taken.
7. Re-Detection: Specify the column used for detection ranking after the recommended actions are taken.
8. Risk Indicator: Specify the column used as the risk indicator column after the recommended actions are taken.

In the built-in template, the index columns were specified and you don't need to do it again.

## 2. Risk Indicator

Next, you need to specify the [risk indicator number](https://www.iqasystem.com/news/risk-priority-number) you use from the below list:

1. **RPN** stands for Risk Priority Number. RPN formula: Severity x Detection x Occurrence.
2. **SOD** stands for Severity - Occurrence - Detection. SOD formula: 100 x Severity.
3. **CN** stands for Critical Number. CN formula: Severity x Occurrence.
4. **None** means not using a number indicator, but you can use other kinds of indicators. For example, a color indicator.

**Note**: If you select None, you can not evaluate with **Top Risks** or **Threshold** method because those methods are quantitative methods. However, Risk Matrix method will work

## 3. Auto Evaluation Method

Next, you must specify how you want to [evaluate the risk](https://www.iqasystem.com/news/risk-priority-number) from the below list:

### Top Risks

For example, due to the limitation of your resources, you only want to focus on the 5 highest risks in your FMEA and consider the next 5 risks that have lower risk levels.

Here is how to evaluate with Top Risks

![](https://www.iqasystem.com/wp-content/uploads/Auto-Evaluation-Top-Risks.png)

1. Check the **Top Risks** under **Auto Evaluation Method** section.
2. On **Quantity of item to be improved**, input the number of items you want to improve.
3. On **Quantity of item to be considered**, input the number of items you want to consider.

### Threshold

This option prioritizes the risks that need to be addressed by defined limitations. Here is how to do it:

![](https://www.iqasystem.com/wp-content/uploads/Auto-Evaluation-Threshold.png)

1. Select **Threshold** in **Auto Evaluation Method**
2. from **Acceptable if lower than**, specify the limit that risk will be acceptable by your team or organization.
3. from **Need improvement if larger than or equal to**, specify the limit that risks will need to be addressed by recommended action.

### Risk Matrix

This option prioritizes the risk by a defined matrix of Severity and Occurrence.

![](https://www.iqasystem.com/wp-content/uploads/Auto-Evaluation-Risk-matrix.png)

1. Select the **Risk Matrix** option in Auto Evaluation Method.
2. In the **Risk Matrix**, select a cell representing the combination of Severity (horizontal axis) an Occurrence (vertical axis) you want to change.
3. Select the risk level in three 3 categories: High Risk (Red), Medium Risk (Yellow) and Low Risk (Green).
   1. High Risk: Must be reduced or eliminated.
   2. Medium Risk: To be considered.
   3. Low risk: Acceptable risk. No action required.

## 4 Evaluate

OK, now you can hit the button. You have can use one or both of the evaluation buttons:

![Evaluation button](https://www.iqasystem.com/wp-content/uploads/Evaluation-button.png)

1. Evaluate before improvement: Evaluate before recommended actions are taken.
2. Evaluate after improvement: Evaluate after recommended actions are taken.